| Sl. No. |
Client |
Project |
Job Description |
| 1. |
Maharashtra State Electricity Board |
New Parli Thermal Power Project, Stage-I (1x250MW )
|
Design, Supply, Fabrication, Erection, Testing & Commissioning of Fuel Oil Storage & Handling System on turnkey basis along with related Civil, Mechanical, Electrical & Instrumentation Works. |
| 2. |
National Thermal Power Corp., Noida, (U.P) |
Sipat Super Thermal Power Project, Stage-II (2x500 MW)
|
Design, Supply, Fabrication, Erection, Testing & Commissioning of Fuel Oil Unloading/Storage and Handling System Package on turnkey basis. |
| 3. |
Punj Lloyd Ltd., Gurgaon/ Rajasthan Rajya Vidyut Utapadan Nigam, Jaipur |
Chhabra Thermal Power Project, 2x250 MW
|
Design, Supply Fabrication, Erection, Testing & Commissioning of Fuel Oil Storage & Handling System on turnkey basis along with design of Civil Works. |
| 4. |
National Thermal Power Corp., Noida, (U.P) |
Sipat Super Thermal Power Project, Stage-II (2x500 MW)
|
Ash Water Recirculation System for Sipat Super Thermal Power Project Stage-II (2x500 MW), Including Civil, Mechanical, Electrical and Instrumentation jobs. |
| 5. |
BALCO, Korba |
1200 MW TPP at Korba Plant
|
Intake Water Supply Pipeline for 1200 MW TPP including Civil, Mechanical, Electrical & Instrumentation Works. |
| 6. |
National Thermal Power Corp., Noida, (U.P) |
Vindhyachal Super TPP
|
Design, Engineering, Manufacturing, Supply of Ash Water Recirculation Package for Vindhyachal TPS for Stage I & II including 1000mm NB x 6300 RM and 700 NB x 5500 RM Pipelines with total pumping capacity of about 10,000M3/hr. The Total work on EPC basis consists of Pipelines, Pumps, Electrical, Civil & Instrumentation Works. |
| 7. |
Jindal Steel & Power Ltd.,
New Delhi |
Raigarh Power Plant
|
Make-up Water Piping Works for Raigarh Plant along with related Pumping and Electrical Works. |
| 8. |
National Thermal Power Corp., New Delhi |
Kayamkulam C.C.P.P.(1x400 MW)
|
Design, Engineering, Supply, Fabrication, Erection, Testing and Commissioning of Make-up Water Piping System at Kayamkulam 400MW Combined Cycle Power Project with 8 kms of 550mm Dia Pipeline & Total Pumping Capacity of over 2000 M3/hr. |
| 9. |
Rajasthan State Electricity Board Jaipur/Development Consultants |
2 X 250 MW Suratgarh Power Project
|
Fuel Oil Handling and Storage System Installation including Civil , Mechanical, Electrical, and Instrumentation works on turnkey basis. |
| 10. |
Bharat Gears Limited, Faridabad |
Gear Manufacturing Plant
|
Design, Supply, Erection, Testing and Commissioning of Propane & HSD Storage and Handling System, Plant Utility Piping System and Total Plant Electrical Works. |
| 11. |
Hetauda Cement Ind. Limited, Nepal |
Cement Plant
|
Design, Manufacture, Supply & Installation of all Machinery Equipment & Piping, Valves & Accessories of Plant Utility Services including Fuel Oil Storage and Unloading System. |